- This is an appeal
with permission of Clarke LJ on limited grounds from a judgment dated 15th
April 2003 given by Mr Julian Flaux QC, sitting as a deputy High Court judge
in the Commercial Court. The appellants are Cine Bes Filmcilik ve Yapimcilik
A.S. (a Turkish cable television company which I shall call "Cine 5")
and Avrupa Ve Amerika Holding A.S. ("Avrupa"). They have not renewed
their application to appeal on other grounds on which Clarke LJ refused permission
on paper. The first respondent is United International Pictures ("UIP"),
a joint venture company established by the second, third, and fourth respondents,
Paramount Pictures International (a division of Viacom International (Netherlands)
B.V.), Universal Studios International B.V. and MGM International Television
Distribution, Inc. The second, third and fourth respondents are described
in relevant licence agreement as "the Studios".
- The proceedings
arise out of a licence agreement signed by the parties and dated as of 1 May
2000. The parties had previously signed a letter dated 4th May
2000, by which they undertook to enter into such a licence agreement in the
form of schedule 1 to that letter. The background is that there had been a
previous licence between UIP and Cine 5 dated February 1994. This had given
rise to claims by UIP against Cine 5 and Avrupa as well as a counterclaim,
both due for trial in June 2000. The letter dated 4th May 2000
recorded the terms on which the parties had agreed to resolve that litigation.
Upon receipt by UIP of US$3,863,090 and an acceptable letter of credit and
upon withdrawal by Cine 5 and Avrupa of their counterclaims, UIP agreed irrevocably
to withdraw its claims. The parties’ signatures in respect of the agreement
in schedule 1 were held by the opposite parties’ solicitors to the order of
the signatories pending receipt by UIP of such sum and letter of credit, and
such agreement was expressly provided to be null, void and of no effect should
such sum and the letter of credit not be received or should the counterclaims
not be withdrawn. These pre-conditions were in the event performed and so
the licence agreement became unconditional.
- The licence
agreement was expressed to be
….
between United International Pictures ("UIP"/"Licensor").
Cine Bes Filmcilik ve Yapimcilik A.S. (the "Licensee"). Avrupa
Ve Amerika Holding A.S. ("Guarantor"), Paramount Pictures
International, a division of Viacom International (Netherlands) B.V. ("Paramount"),
Universal Studios International B.V. ("Universal") and MGM
International Television Distribution, Inc. ("MGM") (Paramount,
Universal and MGM are collectively herein the "Studios" and
individually a "Studio") …."
Under
the agreement Cine 5 as the Licensee received and undertook obligations in
respect of an
"Exclusive
licence for exhibitions of available UIP titles (the "Films")
on the Licensee’s encrypted Pay Movie Channel "Cine" (the "Movie
Channel")."
The
start date of the licence was 1st May 2000 and its "Expiration
Date" 31st March 2003. UIP also granted
"protection
against authorised exhibitions of the same Language of Transmission on basic
cable and free TV (together herein "Free TV") and Pay TV in the
Territory during a Film’s Licence Period"
[and]
protection
against authorised promotions of the Films on Free TV in the same Language
of Transmission during such Film’s Licence Period".
The
"Territory" as defined consisted of Turkey and Turkish-language
Cyprus.
- The agreement
also contained in clause 10.B an "Option to Renew" whereby:
"Each
of Paramount, Universal and MGM or any of their subsidiaries, affiliates or
associated companies shall each separately have an option (i.e. three options
in the aggregate) to require Licensee to enter into a five (5) year pay television
output/re-run licence agreement with them commencing upon the Expiration Date,
the terms of each such new agreement to be the same as those herein set out
…..
[The
clause then went on to provide certain exceptions to the principle that the
terms should be the same.]
The
three options herein above set out shall be exercisable by notice in writing
to Licensee at any time on or before 1 October 2002 and can for the avoidance
of doubt, be exercised by each Studio, or any of its subsidiaries, affiliates
or associated companies separately and independently of each other."
- Under clause
14(c) i) Cine 5 was bound to provide and maintain
"one
or more …. Irrevocable Standby Letters of Credit in the form set out in Appendix
C or such other form as shall be acceptable in all respects to UIP from a
US bank reasonably approved by UIP which are to be valid for 1 year (the "LCs")"
Any
such letter of credit were to be for an aggregate amount not less than US$5
million; and were to be
"renewed
for further annual terms not less than 15 days prior to their expiry and ….
to remain in effect until 3 months after the end of the Licence Period of
the last Film licensed hereunder."
Cine
5’s associated company, Avrupa, confirmed under clause 14(ii) that it would
guarantee Cine 5s’ obligations under the agreement, and signed the agreement
accordingly.
- Clause 16 provided
for an "AB Amount" of US$4,836,155, and for an "AB Account",
consisting of "the AB Amount held by the Licensee and not yet used to
date". It went on that:
"UIP
and/or the Studios, their subsidiaries, associated companies and affiliates
may use the AB Amount in the AB Account at any time before the Expiration
Date in Exchange for:
(a) advertising
of products of UIP, and/or the Studios, their subsidiaries, associated companies
and affiliates as follows .…
(b) barter
time as follows ….
Upon
any termination by UIP of its obligations hereunder, whether pursuant to the
provisions of Clause 17 below or otherwise at law or in equity the full outstanding
amount of the AB Amount in the AB Account shall immediately become due and
payable by Licensee to UIP in US dollars. For the avoidance of doubt Guarantor
acknowledges that the payment of such sums constitutes part of the "Guaranteed
Obligations" under the Guarantee."
Clause
17 read:
"17.
"Termination: Without prejudice to any of UIP’s rights and remedies at
law or in equity in respect of any defaults hereunder by Licensee or Guarantor,
it is expressly agreed that if at any time UIP is not secured by LCs or by
the proceeds of a drawdown in full of the LCs for any Film with a current
Availability Date, UIP shall have the right, exercisable by notice in writing
to Licensee, and without prejudice to any other rights or remedies available
to it in law or in equity in respect of such breach, to accelerate the payment
of all Licence Fees that would fall due to UIP hereunder in respect of all
Films listed in Appendix B, which sum shall thereupon become immediately due
and payable by Licensee to UIP, and to terminate all its future obligations
to Licensee hereunder, whereupon the AB Amount shall become payable in accordance
with Clause 16 above, and all rights licensed in respect of all Films shall
terminate and revert to UIP and Licensee shall have no further rights (including
exploitation rights) in connection with any such Films. In the event of any
such termination Licensee shall pay to UIP in addition to all Licence Fees
due and all damages sustained or incurred as a result of such termination
all actual and reasonably incurred enforcement costs of UIP including those
incurred by UIP in connection with the Litigation up to and including the
date upon which the Court Order dismissing the legal proceedings in the High
Court of Justice between UIP and Licensee and Guarantor (case no. HQ99-04130)
is sealed."
Clause
20 provided for interest on late payments at 3% above US Prime Rate, compounded
monthly, and payable from the date a payment fell due under the agreement.
Clause 35 provided:
"Termination
or suspension of this Agreement for whatever cause shall be without prejudice
to the accrued rights of either party. Notwithstanding termination of this
Agreement (for whatever cause) all obligations of the Licensee under this
Agreement shall where relevant survive termination and the Licensor shall
be entitled to require performance of such obligations."
- In 2001 the
Turkish government abandoned the crawling peg exchange rate mechanism (which
tied the Turkish lire to a basket of currencies including the US dollar) and
allowed the lire to float. Thereafter, Cine 5 defaulted in the payment of
licence fees due under the agreement and failed to renew any US dollar letter
of credit under clause 14(i). On 5th June 2002 solicitors for the
respondents wrote to Cine 5 claiming on behalf of UIP and the Studios to terminate
in accordance with clause 17 and to accept Cine 5’s defaults as repudiatory
breaches of the agreement. Their letter claimed payment to UIP of (a) licence
fees due up to the date of such termination (amounting in fact to US$ 4,017,323.65),
(b) licence fees which would have become payable up to the Expiration Date,
(c) the full AB Amount of US$4,836,155 (no part of this having been utilised),
(c) litigation costs in respect of the proceedings withdrawn when the agreement
as of 1 May 2000 was entered into, (d) damages in respect of all licence fees
that would have fallen due to the Studios during the five year option period
set out in clause 10B of the agreement and (e) interest on these sums at the
rate of 3% above US prime rate provided by clause 20. The present proceedings
were commenced on 29th July 2002, making the like claims - save
that damages related to the alleged loss of the five year option are now claimed
by the Studios, which also claim interest at a commercial rate rather than
at 3% per annum under clause 20.
- The matter came
before Mr Julian Flaux QC on an application by the respondents for summary
judgment. The appellants raised a number of defences: (1) that the whole agreement
was frustrated, (2) that clauses 16 and 17 were unenforceable penalty clauses,
in so far as they provided for payments on termination for breach by Cine
5, (3) that there were triable issues of construction, going to the quantum
recoverable under clause 17, (4) that there were triable issues relating to
the Studios’ claims for loss of the options contained in clause 10.B; in this
last connection the appellants contended: (i) that such options were separate
contracts or severable, and survived any termination by UIP of the agreement,
(ii) that the Studios caused their own loss, by failing to exercise the options
prior to UIP’s termination of the agreement and (iii) that there should be
a trial as to whether the Studios would in fact have exercised their options.
The judge rejected all these defences. Permission to appeal was granted only
in respect of and this appeal is confined to points (2) and (4). The question
is in each case whether the appellants have shown any real prospect of a successful
defence or any other reason for a trial. Most of the issues are issues of
law and/or construction, which both parties have invited us to determine finally,
one way or the other, at this point. However, if and to the extent that we
conclude that clauses 16 and 17 appear arguably penal, the respondents submit
that we should direct a trial to determine in the light of factual evidence
whether they should nevertheless be regarded as containing genuine pre-estimates
of loss.
- Point (2)
– are clauses 16 and 17 unenforceable as penalty clauses? It is not suggested
that clause 17 is invalid in so far as it embraces or confirms the appellants’
obligation to pay licence fees already accrued due to UIP as at the
date of termination of the agreement. The clause in that respect merely reflects
a pre-existing and continuing obligation. Nor is the clause in any way untoward
in stipulating for termination of all UIP’s future obligations. That would
anyway follow from UIP’s exercise of its contractual right to terminate for
Cine 5’s breach.
- The appellants
submit that the rest of the clause must be viewed as a whole, and that it
is invalid so far as it purports to provide for a large number of different
consequences, all favourable to UIP, in such as way as would in the ordinary
course over-compensate UIP for any loss suffered from the termination. These
consequences are (i) the accelerated payment of all future licence fees which
would have fallen due for payment to UIP up to the Expiration Date, (ii) payment
of the AB Amount, (iii) the termination and reversion to UIP of all rights
in connection with currently licensed films, (iv) payment of damages and (v)
payment of all actual and reasonably incurred enforcement costs of UIP, including
those incurred in the litigation withdrawn in consideration of the making
of the agreement.
- The general
scope of the law relating to penalties was identified by Lord Browne-Wilkinson
giving the advice of the Privy Council in Workers Trust Bank Ltd. v. Dojap
Ltd. [1993] AC 573:
"In
general, a contractual provision which requires one party in the event of
his breach of the contract to pay or forfeit a sum of money to the other party
is unlawful as being a penalty, unless such provision can be justified as
being a payment of liquidated damages being a genuine pre-estimate of the
loss which the innocent party will incur by reason of the breach. One exception
to this general rule is the provision for the payment of a deposit (customarily
10% of the contract price) on the sale of land. ….."
- The classic
distinction drawn by Lord Dunedin in Dunlop Pneumatic Tyre Company v. New
Garage and Motor Company Ltd. [1915] AC 79, 86f was between a payment
on breach stipulated as in terrorem of the offending party and a genuine
covenanted pre-estimate of damage. Lord Dunedin added that the question was
one of construction of each contract, to be decided as at the time of its
making, not the time of breach. He offered as tests which might prove "helpful,
or even conclusive", these:
"a)
It will be held to be penalty if the sum stipulated for is extravagant and
unconscionable in amount in comparison with the greatest loss that could conceivably
be proved to have followed from the breach ..….
(b)
It will be held to be a penalty if the breach consists only in not paying
a sum of money, and the sum stipulated is a sum greater than the sum which
ought to have been paid ….. This though one of the most ancient instances
is truly a corollary to the last test. Whether it had its historical origin
in the doctrine of the common law that when A. promised to pay B. a sum of
money on a certain day and did not do so, B. could only recover the sum with,
in certain cases, interest, but could never recover further damages for non-timeous
payment, or whether it was a survival of the time when equity reformed unconscionable
bargains merely because they were unconscionable ….. is probably more interesting
than material.
(c)
There is a presumption (but no more) that it is penalty when "a single
lump sum is made payable by way of compensation, on the occurrence of one
or more or all of several events, some of which may occasion serious and others
but trifling damage".
On
the other hand:
(d)
It is no obstacle to the sum stipulated being a genuine pre-estimate of damage,
that the consequences of the breach are such as to make precise pre-estimation
almost an impossibility. On the contrary, that is just the situation when
it is probable that pre-estimated damage was the true bargain between the
parties….."
- Although the
phrase in terrorem has appeared in many cases since Dunlop,
there is force in Lord Radcliffe’s comment in Campbell Discount Co. Ltd.
v. Bridge [1962] AC 600, 622, that
"I
do not find that that description adds anything to the idea conveyed by the
word "penalty" itself, and it obscures the fact that penalties may
quite easily be undertaken by parties who are not in the least terrorised
by the prospect of having to pay them …."
A
more accessible paraphrase of the concept of penalty is that adopted by Colman
J in Lordsvale Finance Plc v. Bank of Zambia [1996] QB 752, 762G, when
he said that Dunlop Pneumatic Tyre showed that:
"whether
a provision is to be treated as a penalty is a matter of construction to be
resolved by asking whether at the time the contract was entered into the predominant
contractual function of the provision was to deter a party from breaking the
contract or to compensate the innocent party for breach. That the contractual
function is deterrent rather than compensatory can be deduced by comparing
the amount that would be payable on breach with the loss that might be sustained
if breach occurred."
- In Philips
Hong Kong Ltd. v. The AG of Hong Kong (1993) 61 BLR 49, the Privy Council
in advice delivered by Lord Woolf underlined test (a) suggested by Lord Dunedin,
endorsed the view that the "court should not be astute to descry a ‘penalty
clause’" and emphasised that it would "normally be insufficient
…. to identify situations where the application of the provision could result
in a larger sum being recovered by the injured party than his actual loss"
(pp.58-59). However, Lord Woolf went on:
"A
difficulty can arise where the range of possible loss is broad. Where it should
be obvious that, in relation to part of the range, the liquidated damages
are totally out of proportion to certain of the losses which may be incurred,
the failure to make special provision for those losses may result in the "liquidated
damages" not being recoverable. (See the decision of the Court of Appeal
on very special facts in Ariston SRL v Charly Records Ltd (1990) The
Independent 13 April 1990.) However, the court has to be careful not to
set too stringent a standard and bear in mind that what the parties have agreed
should normally be upheld. Any other approach will lead to undesirable uncertainty
especially in commercial contracts "
- I have also
have found valuable Colman J’s further observation in Lordsvale at
pp.763g-764a, which indicate that a dichotomy between a genuine pre-estimate
of damages and a penalty does not necessarily cover all the possibilities.
There are clauses which may operate on breach, but which fall into neither
category, and they may be commercially perfectly justifiable. In the case
before him, Colman J was concerned with a provision for prospective increase
in the interest rate payable by a borrower, following the borrower’s default.
He said that, although the payment of liquidated damages is "the most
prevalent purpose" for which an additional payment on breach might be
required under a contract
"….
the jurisdiction in relation to penalty clauses is concerned not primarily
with the enforcement of inoffensive liquidated damages clauses but rather
with protection against the effect of penalty clauses. There would therefore
seem to be no reason in principle why a contractual provision the effect of
which was to increase the consideration payable under an executory contract
upon the happening of a default should be struck down as a penalty if the
increase could in the circumstances be explained as commercially justifiable,
provided always that its dominant purpose was not to deter the other party
from breach."
- Another decision
relied on by the respondents before us is Oresundsvarvet AB v. Marcos Diamantis
Lemos (The "Angelic Star") [1988] 1 Ll.R. 122. The Court of
Appeal held that it was not penal for a provision to accelerate payment of
capital sums, due under a "delivery credit" arrangement, upon a
failure to comply with the conditions upon which credit was extended. The
delivery credit had been made available to the purchaser as an "option",
in default of exercise of which the full price was payable in cash. So there
was nothing penal about providing for payment of the capital to be accelerated
on any default (provided that the interest which would have been payable for
deferring payment under the credit was not also payable).
- Consequences
(i) and (ii) would afford the respondents 100% of the benefits expected from
the running of the licence for its full course to the Expiration Date, without
allowing any credit for (a) UIP’s retention and ability to exploit the films
which would have become available to be licensed to Cine 5 during the rest
of the licence period and (b) UIP’s recovery of, and ability to exploit for
the balance of their licence periods, films with licences still current on
5th June 2002. The appellants point out that licence fees for any
film within (b) accrued due in full as soon as such film became available
(see clause 14(b)), and have been paid or are recoverable accordingly (see
paragraph 11 above).
- The respondents
accept that consequence (i) may be penal, although they do not concede that
it is and wish to contend the contrary at trial. However, they submit that
the clause can be severed as regards consequence (i), leaving the other consequences
unaffected. The particular consequences on which argument therefore centres
are consequence (ii) (payment of the AB Amount) and, so far as it provides
for payment of costs incurred in the litigation withdrawn in consideration
of the making of the agreement, consequence (v). I focus for the moment on
consequence (ii) alone.
- As an illustration
of severance in this area, the respondents refer to The "Angelic Star"
[1988] 1 Ll.R. 122. Neill LJ at p.126f (left) and Ralph Gibson LJ at p.126e
(right)-127g (left) there rejected an argument that, if the clause included
a penalty element (by purporting to make future interest payments immediately
payable on default occurring under the loan), that also invalidated the provision
accelerating the payment of the outstanding loan. As Ralph Gibson LJ said
at p.126-127:
"The
doctrine relating to penalties is not a rule of illegality: it is a rule by
which the Court refuses to sanction legal proceedings for recovery of a penalty
sum, a rule which the Court had produced and maintained for purposes of public
policy: see per Lord Radcliffe: Campbell Discount Company Ltd. v Bridge
[1962] A.C. 600 at p.622. The rule is, in my judgment, not designed to strike
down any more of a lawful contract than is necessary to give effect to the
Court’s purpose of applying public policy; and, moreover, the rule should
be applied so as to interfere as little as possible with the proper enforcement
of a lawful contract according to its terms. Parties to a contract are free
expressly to stipulate not only the primary obligations and rights under the
contract but also the secondary rights and obligations, i.e. those which arise
upon non-performance of any primary obligation by one of the parties to the
contract: see per Lord Justice Diplock (as he then was): Robophone Facilities
Ltd. v Blank, [1966] 1 W.L.R. 1428 at 1446B. Lord Justice Diplock continued:
……But
the right of parties to a contract to make such a stipulation is subject to
the rule of public policy that the court will not enforce it against the party
in breach if it is satisfied that the stipulated sum was not a genuine estimate
of the loss likely to be sustained by the party not in breach, but was a sum
in excess of such anticipated loss and thus, if exacted, would be in the nature
of a penalty or punishment imposed upon the contract-breaker. Where the court
refuses to enforce a "penalty clause" of this nature, the injured
party is relegated to his right to claim that lesser measure of damages to
which he would have been entitled at common law for the breach actually committed
if there had been no penalty clause in the contract."
- The Angelic
Star was concerned with a delivery credit, essentially a contract for
a loan, although provided as part of a shipbuilding contract. The loan was
to be repaid by bills of exchange accepted by the vessel’s purchaser, and
was to be secured by mortgage of the vessel. On default, the contract provided
for repayment of the loan and enforcement of the security. The vessel was
duly arrested and sold, and her proceeds credited against the accelerated
obligation to repay the loan. What Neill and Ralph Gibson LJJ were accepting
was the possibility of severing a provision for additional monetary payment,
in the amount of the interest payments which would only have been earned if
the loan had remained outstanding.
- The present
contract is more complex in nature than a loan. Its termination did not just
leave the respondents out of pocket. It restored proprietary benefits which
the respondents thereby became able to exploit, for whatever worth they might
have. And it did not do this by way of security for payment of monetary obligations.
Clause 17 contains a scheme providing for the monetary consequences of termination
for breach. That on any view requires care, since termination may occur sooner
or later in the course of a long term licence contract and market conditions
at the date of termination may greatly affect the actual loss suffered by
the terminating party. But the critical point is that the innocent party’s
actual loss in such a case is a single "net" amount derived by drawing
a balance sheet (cf Chitty on Contracts, 28th Ed. Vol. 1, para.
27-001). On the one side are benefits lost and on the other side benefits
received by reason of the termination. Clause 17 does not attempt any balance.
It simply lists, as consequences (i) and (ii), particular monetary benefits
lost by reason of the termination. For good measure, it adds, as consequence
(iv), a general provision for payment of damages. That underlines the fact
that consequences (i) and (ii) are introduced as minima, intended to be recoverable
without further enquiry. The resulting problem is that clause 17 contains
no contractual provision or mechanism for giving any credit, against sums
recoverable under consequences (i) and (ii), in respect of the proprietary
benefits recovered on termination by the respondents.
- Consequence
(iii) does not provide for any monetary payment, and no question therefore
arises about its validity. It is an understandable commercial provision, in
that it secures a clean break, by restoring to UIP all its property immediately.
Nevertheless, it yields a benefit which would at common law have to be brought
into account in any assessment of the respondents’ actual loss resulting from
a termination. The issue is thus not about the consequence (iii), but about
the validity of consequences (i) and/or (ii) in the light of both consequence
(iii) and the more general failure to provide any mechanism for crediting
any value possessed by films which would have been the subject of future licences.
If both consequences (i) and (ii) are valid, the effect must be to over-compensate
the respondents - unless it was contemplated in May 2000 that the relevant
films would be absolutely or substantially valueless in the respondents’ hands
apart from the licence to the appellants. That qualification does not on its
face represent a probable factual hypothesis, and (in the absence of any evidence
to support it) on any view merits trial. It is true that the actual receipts
from re-licensing films to the one other Turkish cable television channel
(Digiturk, which it appears has 600,000 viewers) appear to have been relatively
small, but that was following the collapse of the Turkish currency and in
depressed market conditions which were evidently not foreseen on either side
in May 2000.
- The respondents
submit that the problem can be avoided by severing clause 17, so far as it
provides for consequence (i). That would leave consequence (ii) (payment of
the AB Amount). But if consequence (i) is or may be penal, because it fails
to allow for the benefit of the value of future licences, the failure to make
any similar allowance in respect of the value, during the balance of their
current licence periods, of films subject to licences current as at 5th
June 2002 is only different in degree. Licences current as at 5th
June 2002 could have up to either 12 or 15 months outstanding, depending on
the films to which they related (cf clause 13(a) and (b)). The respondents’
actual loss from termination can only be calculated by allowing for the value
of films during the balance of licence periods current at termination. The
respondents’ suggestion (without any evidence) that the parties would not
have contemplated that films recovered would have any or any substantial value
during the balance of their current licences merits trial.
- Arguments that
the court should not be astute to ‘descry a penalty clause" and should
be careful not to apply too stringent a standard diminish in force when (a)
the whole scheme of clause 17 ignores one side of the balance sheet and (b)
the respondents accept, as a result, that at least consequence (i) is arguably
penal.
- It is no answer
to the problem identified in paragraph 23 that the only specific monetary
obligation imposed under clause 17, apart from consequence (i), consists in
an obligation to pay the AB Amount. The respondents’ actual loss on termination
is a loss arising from drawing an overall balance. The AB Amount derives from
a particular clause of the contract. Actual loss on termination is not viewed
or calculated on a clause by clause basis. It is an overall loss.
- The AB Amount
represents the value of advertising or barter time to which the respondents
would have been entitled had the licence run its full course. The respondents
had not in the period of over 2 years since the inception of the licence used
any of their entitlement to such time. It might be questioned whether they
would have used any or all of it before 31st March 2003, or what
loss they may have suffered from having (at least notionally) to purchase
equivalent time elsewhere. On the other hand, the appellants were in breach
for much of the first two years, and, more importantly, the question whether
consequence (ii) constitutes a genuine pre-estimate of the benefit lost through
termination should be viewed as at the date of entry into of the licence,
when Turkish market conditions were evidently buoyant, not as at 5th
June 2002, when they were very depressed. So, if this were no more than a
contract for provision of air time to the value of the AB Amount, I would
be very unenthusiastic about any argument that a provision for payment of
the AB Amount on breach was penal, rather than a genuine pre-estimate of the
loss suffered through non-availability of time on the appellant’s channels.
- The problem
arises because the AB Amount is only one component in an overall balance,
and any genuine pre-estimate of actual loss would have to relate to the net
overall balance, not to the amount of a single component. I do not, in these
circumstances, consider that consequence (ii) can stand independently, when
the contract makes no allowance for the credit received from the recovery
of the benefit of film licences. Even if one treats consequence (i) as deleted,
one would suppose that films under current licences would, in the more benign
market conditions existing in May 2000, have been expected to have had some
value on termination during the balance of their licence periods.
- It is also no
answer to the problem identified in paragraph 23 that, if consequence (i)
is penal, the respondents will have a common law claim to damages against
which any appropriate allowances for such value could be set. The respondents
do not of course accept that consequence (i) is penal. But, assuming that
it is, the loss of future licence fees may not have caused the respondents
any damages (e.g. if at termination the market value of future films were
to equal or exceed the value of such fees). Clause 17 provides no mechanism
in that event for crediting, against the AB Amount payable under consequence
(ii), the value, during the balance of their current licence periods, of films
subject to licences current as at 5th June 2002.
- For these reasons,
I would, with respect for the judge’s careful analysis, conclude that he was
wrong to treat in isolation one component of the respondents’ potential loss
on termination, the payment of the AB Amount. The actual loss which the respondents
could be expected to suffer on termination cannot be compartmentalised in
this way. The operation and validity of clause 17 also requires to be viewed
overall. The problem on this basis is that the clause looks only at one side
of the balance sheet, and fails to address the countervailing benefits which
would, on their face, appear likely to have been contemplated by the parties
as flowing from any termination. I would therefore hold that the appellants
have shown a triable issue to the effect that both consequences (i) and (ii)
in clause 17 are penal. Whether they are actually penal must be determined
in the light of evidence, in view of the respondents’ contention that the
parties may when contracting have thought that the films recovered on 5th
June 2002 (the subject of future and current licences) would have had no significant
value in the respondents’ hands.
- I turn to consequence
(v), costs. No problem arises so far as this covers costs of the present enforcement
proceedings. In that respect, clause 17 was not stipulating for a sum which
was penal. Strictly, it was not even stipulating for a loss in respect of
which it could have claimed damages. Although in one sense the present proceedings
were "caused" by the termination, their immediate cause is the appellants’
alleged failure to meet their secondary obligations arising from the termination.
Any right to costs is thus at common law generally a matter of judicial discretion
(as indeed is any claim to interest on sums unpaid). But clauses providing
for the recovery of enforcement costs or for interest are familiar, e.g. in
loan contracts. Such clauses have a legitimate commercial purpose, which takes
them outside the scope of the law relating to penalties.
- What then of
the position relating to the costs of the previous litigation? The appellants
submit in relation to them that the contract introduces a claim, on termination,
which fails to reflect any loss which could be recoverable in law; alternatively,
if there is any basis on which such a claim could be made, it is inconsistent
with that on which consequences (i) and (ii) proceed, and would give rise
to dual recovery on opposite hypotheses. In either case, they submit, consequence
(v) must be regarded an invalid penalty.
- The principal
feature of the prior litigation costs is that these are actual costs, which
the respondents incurred and were seeking in the prior litigation, but which
they agreed to forego when a settlement was reached and when a new licence
agreement was made. This feature differentiates the present case from the
type of penal provision familiar from the authorities, which involves a payment
which either does not reflect or considerably exceeds any actual outgoing
or loss of profit. But the appellants submit that a past outgoing, which could
not have been recovered in damages, is no different in law from a non-existent
or over-estimated loss. They distinguish The Angelic Star as a case
where the loan was an established obligation which was (on one basis or another,
cash or credit) unquestionably enforceable. They accept that, in some circumstances,
a contractual claimant may recover losses incurred or benefits foregone as
a result of entering into a contract. However, that, they point out, would
have to be as an alternative to any claim for the overall loss arising from
breach of the contract (cf Chitty on Contracts 28th Ed. Vol. 1
para. 27-002). So, here, they submit, clause 17 must be penal in so far as
it purports to provide for the recovery both of losses arising from the breach
(consequences (i), (ii) and (iv)) and recovery of costs foregone by entering
into the contract (consequence (v)).
- I do not accept
the appellants’ analysis. Clause 17 provides for payment of the prior costs
"in the event of" such a termination. But I do not consider that
their payment should be regarded as a penalty attached to Cine 5’s breach
of the agreement. Rather, it is one of the terms on which the respondents
were prepared to forego further pursuit of the prior litigation against Cine
5 and Avrupa. There could have been no objection if the respondents had stipulated
for payment of such costs outright, or if they had stipulated for them but
agreed to forego payment as long as the licence agreement was entered into
and duly performed. In relation to the actual costs of prior litigation, I
consider that the parties were free to make any agreement they wished. The
mere fact that they chose to make such costs depend on the (non-)performance
of their fresh licence agreement, foregoing such costs in the meanwhile, does
not mean that the obligation to pay such costs, which has now matured, should
be regarded as a penalty imposed for breach of that agreement. Colman J’s
analysis in Lordsvale of the boundaries of the doctrine relating to
penalties is here in my view of relevance. The agreement regarding past litigation
costs was understandable in the overall context of the settlement of the prior
litigation. It would be wrong to treat it as if it was there to deter Cine
5 from, or to penalise or punish Cine 5 for, any default. It was an understandable
and reasonable commercial condition upon which UIP was prepared to dispose
of the prior litigation, and to enter into the fresh licence. Whether the
benefit thereby obtained in costs requires to be credited against any damages
which may be recoverable in respect of the termination (if all or part of
clause 17 is an unenforceable penalty) does not arise at this stage and need
not be considered.
- Point (4)(i)
– were the options separate contracts or severable, so as to survive any
termination by UIP of the agreement? That one and the same document can
constitute a bundle of separate contracts is clear. Witness, for example,
the position of individual subscribers to a composite insurance, issued by
Lloyd’s and/or insurance companies, as mentioned in Touche Ross & Co.
v. Baker [1992] 2 Ll.R. 207. But it is also clear that, when there is
a bundle of separate contracts, some or all of the subscribers may, as a matter
of construction, be tied together, so that their rights or duties have to
be viewed en bloc. That gave rise to the central issue in Touche
Ross & Co. v. Baker. Lloyd’s syndicates at that time consisted of
individual names. The assured was entitled to operate the relevant extension
clause in relation to one or more particular syndicates differently from the
way in which it operated it in relation to other syndicate(s). It could not
have claimed to operate it differently as between different individuals within
one and the same syndicate.
- I am for present
purposes prepared to accept that the present document contains on analysis
a bundle of contracts, involving the different parties to it to a greater
or lesser extent. To take an obvious point, the guarantor, Avrupa, is only
a signatory and party to it, to the extent of its role as guarantor. UIP is
not expressed to be a party to the option, since it was apparently contemplated
that its activity as the Studios’ joint venture company would not continue
beyond the first licence period. The Studios were not expressed to be parties
to most of the licence obligations relating to the first period. On the other
hand, clause 33 only allows assignments by UIP of "this Agreement, in
such a way that the collective obligations of UIP and/or the Studios afford
substantially the same protection and rights to the Licensee as in this Agreement";
and the arrangements regarding the AB Amount and Account were expressly in
favour of "UIP, and/or the Studios, their subsidiaries, associated companies
and affiliates" - although the final sentence of clause 16 required payment
of the full outstanding AB Amount, upon any termination by UIP of its obligations
under the agreement, to be made "to UIP". Clause 17, dealing more
generally with termination, also provides throughout for payments "to
UIP".
- The conclusion
that the document embraces a bundle of contracts does not determine whether
termination by UIP under clause 17 has any and if so what effect on the options
granted under clause 10.B in favour of the Studios, or whether it leaves them,
as the appellants contend, as surviving independent contracts. The point is
one of construction. The latter conclusion would give rise to a very curious
position. Termination for breach, which might occur at any time during the
first licence, would end any ongoing contractual obligations, as between UIP
and Cine 5 (save those concerned with the winding up of the relationship,
such as clause 17 so far as valid, and clauses 35 to 37). But the options
"to renew" in favour of the Studios would continue to exist and
would be potentially exercisable (until 1st October 2002) for a
fresh, five year period with effect from 31st March 2003. Cine
5 would in the meantime be uncertain where it stood or what alternative arrangements
it could make. The law can cater for flying freeholds, but the suggested analysis
has more in common with levitation.
- In response,
the appellants ask rhetorically what would have happened if one or more of
the Studios exercised an option prior to termination (e.g. here, prior
to 5th June 2002). Any option had to be exercised by latest 1st
October 2002, so it can also be asked what would have happened, if, after
the exercise of an option on say 30th September 2002, the appellants
had broken the contract, perhaps for the first time, leading to its termination
by UIP. I am prepared to assume that, in such circumstances, the Studios’
entitlement to a licence, as a result of the exercise of the option, would
have continued, despite the subsequent termination. There may be a contrary
argument, to the effect that it is a pre-condition of any fresh licence in
favour of the Studios that it should continue as a "renewal" commencing
"upon the Expiration Date" of the original licence. But it is unnecessary
to reach any conclusion on this. The agreement itself distinguishes between
the effect of termination upon "accrued" and other rights: see clause
35. The option to renew cannot itself be regarded as an "accrued"
right, merely because it appears in the agreement from its inception. But
such an option, once exercised, clearly gives rise to an accrued right, in
the form of the Studios’ entitlement to a fresh, five year licence. So, assuming
that the Studios’ and Cine 5’s entitlement to and obligations under such a
licence would survive in such circumstances, that situation is expressly distinguished
from the present by clause 35.
- Reverting to
the present situation, the general intention was obviously that the options
should be exercised and exercisable only by way of continuation (or "renewal")
of the prior licence. That is so, even though the options are expressed to
be in favour of the Studios themselves, rather than the Studios’ joint venture
creature, UIP. What is suggested here is not renewal, but effectively revival
of a fresh relationship by exercise of the option after termination of the
relationship with UIP, and at a time when UIP would be expected to be pursuing
claims under clause 17. If UIP was entitled to and did terminate under clause
17 (e.g. as here, for failure by Cine 5 to provide a letter of credit), it
cannot sensibly have been thought that the Studios should have, or would wish
to have, any such option at such a time. As a matter of construction, therefore,
the option(s) promised to the Studios never became available for execution.
- This leaves
for consideration whether the Studios can claim damages for loss of their
option(s). In my judgment, they can. The grant of the options was part of
the consideration provided under the agreement, to which the Studios were
parties in their own right. Under clause 10.B and under the head of "Option
to renew", Cine 5 agreed that each of the Studios "shall each separately
have an option …. to enter into a five … year …. licence agreement with them
commencing on the Expiration Date". It was a necessary implication of
this positively granted option that Cine 5 would not, by repudiating the original
licence in favour of UIP, prevent the option(s) granted in favour of the Studios
from ever arising. Cine 5’s performance of its own obligations to the Studios’
joint venture company, UIP, cannot be viewed as if it were some sort of frustrating
event or pre-condition, beyond Cine 5’s control, failure of which would simply
render the option inapplicable.
- Point (4)(ii)
– did the Studios cause their own loss, by failing to exercise the options
prior to UIP’s termination of the agreement? The appellants’ submission
is that the Studios could, after Cine 5 fell into breach and at any time up
to UIP’s termination, have exercised the option(s), so as in some way to pre-empt
the effect of any such termination. The submission underlines the unreality
of the appellants’ case regarding exercise of the options. If the Studios’
joint venture company, UIP, was entitled and about to terminate for breach
of the basic licence, the Studios cannot have been obliged to "mitigate"
their potential loss of their options by exercising them, and cannot be regarded
as having "caused" their own loss by failing to do so. To exercise
the option to renew would have involved the Studios committing themselves
to a fresh, five year relationship with Cine 5, in the face of Cine 5’s breach
causing the breakdown of UIP’s first, three year relationship with Cine 5.
No-one could sensibly expect the Studios to do this. Moreover, the whole argument
assumes that the Studios could be said to have caused or failed to mitigate
loss otherwise flowing from the termination by inaction before UIP
treated Cine 5’s breaches as justifying termination of the first licence on
5th June 2002. Prior to that date, Cine 5’s only breaches consisted
in failure to pay for and/or take available films. Such breaches could in
no way be "mitigated" by any exercise by the Studios of their option
to renew.
- Although unnecessary
for my decision, I also see very considerable force in the respondents’ submission
that any exercise by the Studios of the option to renew prior to 5th
June 2002 could well also have led to substantial legal arguments by Cine
5 (the reverse of those now mounted) that the agreement was a composite agreement,
which could no longer be terminated for breach by UIP once it had been affirmed
by the Studios by the exercise of the option.
- Point (4)(iv)
– should there have been a trial of the issue whether the Studios would in
fact have exercised their options? The judge acknowledged that the onus
was on the respondents to prove that the Studios would have exercised their
options. Nonetheless, he held that there was no real prospect, requiring a
trial, of any other conclusion. The claim that the Studios has suffered loss
and damage in respect of its loss of the options is supported by statements
of truth by officers of the respondents, on the basis that the options would
have been more valuable to the Studios than any alternative licensing arrangements
which they would have been likely to obtain: see the particulars of claim
paragraph 8 and the reply paragraph 11. The defence served 13th
September 2002, attested to by officers of the appellants and Avrupa, said
that by March 2003 Cine 5’s subscriber numbers would have been such (i.e.
so depressed) that the Studios would have been able to generate greater revenues
from licensing Turkish cable television rights elsewhere. The respondents’
solicitors’ witness statement dated 20th January 2003 served in
support of the application for summary judgment and based on information from
officers of the respondents responded on this point in paragraph 25, by pointing
to the guaranteed minimum subscriber numbers which would have applied under
the terms of any fresh licence to Cine 5, and to the collapse of actual subscriber
numbers following the collapse of the Turkish economy. When the appellants’
head of acquisitions, Mr Oktar, came to reply on 26th March 2003
he failed to address the response on this aspect at all. He simply pointed
out that none of the respondents had by 5th June 2002 taken any
steps to exercise or given any indication that they were considering exercising
the option. That, as the judge observed, is hardly surprising, bearing in
mind the time available for its exercise on or by 1st October 2002.
One may add that it is even less surprising in circumstances where Cine 5
had been in repeated breach since early 2002 (see the letter dated 5th
June 2002), and UIP and the Studios are likely to have been reviewing their
position regarding termination for some time before 5th June 2002.
- The appellants
also point to evidence that the Studios were unwinding their joint venture
company, UIP. But that, as the judge observed, is entirely consistent with
the agreement, which conferred the options on the Studios, rather than UIP.
The appellants finally submit that there should be a full investigation and
if necessary trial in case material, documentary or oral, emerges which undermines
the respondents’ case that they would have exercised the options, if Cine
5 had performed the original licence in favour of UIP. Like the judge, I do
not think that the appellants have shown any real prospect of a defence that
they would not have exercised the options in the circumstances, which on the
evidence prevailed with regard to the marketing of such Turkish language cable
television films. I would therefore dismiss the appeal on this point also.
- It follows that
in my judgment this appeal should succeed in one respect, in that there should
be a trial not merely of the issue whether clause 17 is penal in providing
for consequence (i) (accelerated payment of all future licence fees), but
also of an issue whether it is penal in providing in addition for recovery
of consequence (ii) (payment of the AB Amount). In other respects, I would
dismiss this appeal. I would, as invited by counsel, also determine positively
that clause 17 is not penal in providing for recovery of the costs of the
prior litigation. The summary judgment awarded to the Studios in respect of
the loss of their options stands.
Lord Justice
Thomas :
- I agree but
wish to add a brief word of my own in relation to the issue as to whether
clauses 16 and 17 were penal, in view of the fact that I have also reached
a different conclusion from that of the Deputy Judge.
- The unusual
feature of the dispute in relation to these clauses arises because in addition
to making the payment of various specified sums due on breach, including the
AB amount, clause 17 also expressly provided for the termination of all the
rights to the films for which payment had already been made or was due. UIP
therefore were in a position to exploit the balance of the licence period
of such films for their own benefit, even though they had been paid in respect
of that period by Cine 5. UIP were not, however, under the terms of the clause
required to bring into account against what was to be paid to them (including
the AB amount) any benefit they received from that exploitation.
- If damages were
to be calculated in the ordinary way for the loss UIP had suffered from breach,
it was accepted by UIP that any benefits that UIP obtained through exploiting
the balance of the period by licensing the films to others would have to be
brought into account; such benefits would be ones arising in the ordinary
course of business as a consequence of the termination. However the contract
provided no mechanism for such benefits to be brought into account under clause
17.
- The short issue
was whether UIP had for the purposes of summary judgment application under
Part 24 shown that there was no realistic prospect of Cine 5 establishing
that clauses 16 and 17 were penal, even though the clauses failed to provide
a mechanism for bringing the benefits of exploitation into account against
sums that were payable, other than those already accrued due.
- It is clear
from the authorities to which reference has already been made by Mance LJ
that a clause may be penal if it cannot be justified as being a genuine pre-estimate
of the loss which the innocent party will incur by reason of the breach. A
decision on whether it is penal involves a careful examination of the circumstances
which is not possible on a Part 24 application. There is, in my view, sufficient
evidence to suggest that it would have been envisaged that on breach, the
termination of the rights to the films for which payment had been made would
confer benefits upon UIP; however, the terms of the clauses make it clear
that these were not to be brought into account against the sums payable on
termination including the AB amount.
- In those circumstances
I cannot reach a final conclusion that the clauses were not penal; they might
not be, but there are two issues. First, in my view the question must be investigated
at trial as to why what appear to be benefits which would accrue to UIP were
not to be brought into account, if the clauses were to operate as a genuine
pre-estimate of the loss to be suffered by the innocent party on breach. A
genuine pre-estimate would ordinarily imply consideration being given to bringing
into account the material and significant matters that went to the ascertainment
of the actual loss suffered by the innocent party. Because there was a failure
to include within the clauses a provision for bringing into account a benefit
to the innocent party that would at first sight have been obvious to the parties
at the time the contract was made, there is, in my view, a real issue as to
whether the clauses were intended as a genuine pre-estimate of the loss. There
might, of course, be reasons why the clauses were not penal, even though the
benefits were not to be brought into account under their terms, but no conclusion
can be reached, in my view, without the investigation appropriate to a trial.
- Second, in my
view clause 17 cannot be severed in the way suggested by UIP so that the AB
amount remained payable, even if the remainder of the clause was penal. The
clause was concerned with the sums to be paid on termination; apart from the
provision which confirmed the obligation to pay the sums already accrued due,
it should be looked at as a whole as to what is to be paid on termination.
If the apparent benefit, arising from the termination of the film rights,
which was to be derived from the opportunity to exploit the balance of the
licence period of films for which Cine 5 had paid, had to be brought into
account, it had to be brought into account against the sums which became payable
on termination including the AB amount. That was because the AB amount was
but one component of the whole of the clause the validity of which depended
on whether it provided for a genuine pre-estimate of the loss.
Lord Justice
Peter Gibson:
- I also agree,
but in deference to the careful and lucid judgment of the judge I too add
a few words of my own on the one point on which we are differing from him.
- I confess that
at one stage I was attracted by the judge’s approach to the AB Amount in para.
27 of his judgment that, like the outstanding fees, the unused AB Amount,
being the agreed value of the free advertising or barter time to be made available
to the Claimants during the course of the contract, was recoverable as a debt
against which no credit for any mitigation fell to be set.
- However, I am
persuaded by Mance L.J.’s judgment that that is not correct. By cl. 17 of
the agreement upon termination "the AB Amount shall become payable in
accordance with Clause 16 above, and all rights licensed in respect of all
Films shall terminate and revert to UIP …." UIP was therefore on termination
to be free to exploit the Films, and provided that it was not foreseen by
the parties at the time of the agreement that that would be of no value to
UIP, there is no reason in principle why that benefit should not be taken
into account in any genuine pre-estimate of loss consequent on termination
to be set against the AB Amount. Whilst the evidence relating to receipts
from licensing to the rival to Cine 5, Digiturk, suggests that the benefit
from exploitation of the Films is likely to be only modest, it is important
to view the matter as at the date of the agreement, when the financial conditions
in Turkey were not as dire as they became in 2001 on the collapse of the Turkish
lira. I therefore agree that there is a triable issue as to whether the provision
for payment of the AB Amount is penal (in addition to the provision for the
payment of future licence fees) and that to that limited extent the appeal
should be allowed.