Case
No: A1/2001/1957
Neutral Citation
No [2002] EWCA Civ 459
IN THE SUPREME
COURT OF JUDICATURE
COURT OF
APPEAL (CIVIL DIVISION)
ON APPEAL
FROM THE TECHNOLOGY AND
CONSTRUCTION
COURT
(HER HONOUR JUDGE
KIRKHAM)
Royal
Courts of Justice
Strand, London,
WC2A 2LL
Date:
12 April 2002
Before
:
LORD
JUSTICE PILL
LORD JUSTICE
MUMMERY
and
LORD JUSTICE LATHAM
Between
:
| |
Parsons
Plastics (Research and Development) Ltd
|
Appellants
|
| |
-
and -
|
|
| |
Purac
Ltd
|
Respondents
|
Paul
Bleasdale QC and Peter Collie (instructed by Paris & Co) for
the Appellants
Antony
Edwards-Stuart QC and Andrew Rigney (instructed by Masons) for the
Respondents
Hearing
date: 28th February 2002
JUDGMENT
: APPROVED BY THE COURT FOR HANDING DOWN (SUBJECT TO EDITORIAL CORRECTIONS)
Lord Justice Pill:
- This is an appeal
from judgments of Her Honour Judge Kirkham given in the Technology and Construction
Court, sitting in Birmingham, and dated 13 and 21 August 2001. Parsons Plastics
(Research & Development) Ltd ("the appellants") were refused summary judgment
in the sum of £222,765.75 (plus VAT and interest) against Purac Ltd ("the
respondents") and a stay to arbitration of the respondents' Part 20 money
claim. The judge granted the respondents summary judgment on their specific
money claim. She ordered an interim payment of £12,000. The appellants were
ordered to pay the respondents' costs.
- The respondents
were engaged by Anglian Water Service as main contractors for the design and
construction of a sewage treatment works at Lowestoft. The respondents engaged
the appellants as sub-contractors, under a written contract, for the supply
of an odour control package at the works. Work under the sub-contract began
in July 2000 although the sub-contract was not signed until 3 October 2000.
- Concern was
expressed about the appellants' lack of progress in the work and matters came
to a head in December 2000. On 30 November 2000, at the request of the appellants,
the respondents paid a sum of £30,963 direct to the appellants' steel supplier.
By letter dated 11 December 2000 the appellants requested the respondents
to make a further direct payment to their suppliers in the sum of about £100,000.
That sum was not paid but the respondents agreed to some rescheduling. On
20 December 2000 the appellants applied for payment number 3 of a series of
payments due when certain milestones, set out in the third schedule to the
written agreement, had been reached. A total sum of £261,749.76 was claimed.
The respondents declined to pay that sum claiming on 21 December that the
sub-contract works had not reached the required stage. The respondents also
claimed that the appellants had failed to meet delivery dates and, following
warning letters, wrote to the appellants on 11 January 2001 purporting to
give notice that they were taking over the remaining part of the sub-contract
works (pursuant to Clause 20(c) of the sub-contract) on the ground that the
appellants had failed to comply with their obligations under the contract.
On 12 January 2001 the respondents ejected the appellants from the site. On
4 April 2001, the appellants referred the dispute as to whether they were
entitled to payment under application number 3 to adjudication. Mr Daniel
Atkinson FICE, FCIArb, accepted appointment as adjudicator on the following
day.
- An issue arose
upon the jurisdiction of the adjudicator on the ground that the relevant work
was not a "construction operation" as defined by the Housing Grants, Construction
and Regeneration Act 1996 ("the Act"). During submissions about jurisdiction,
the respondents' solicitor stated in writing, on 3 May 2001:
"¼
we confirm that our client is prepared to submit to your jurisdiction under
the terms of the sub-contract only, in respect of the dispute referred to
you.
It
is our clients position that you would not have jurisdiction to conduct an
adjudication in relation to this issue under the provisions of [the Act] for
the reasons set out in our letter of 2nd May notwithstanding this,
our client is prepared to submit to your jurisdiction in respect of an adjudication
of matters properly referred to you to be conducted under and in accordance
with the provisions of the contract between the parties ¼ "
- Notwithstanding
that form of acceptance, the adjudicator did rule on the question whether
the work was a "construction operation" within the meaning of the Act and
concluded on 4 May 2001 that it was not. It was common ground that the Act
did not apply to the adjudication.
- On 17 May 2001
in the appellants' favour, the Adjudicator found that they aware entitled
to payment under Clause 17(a) of the sub-contract in respect of individual
tasks which had been completed rather than having to wait until the whole
of the sub-contract works had been completed. The appellants were held to
be entitled to payment of 40% of the value of the completed activities. The
respondents were ordered to pay the sum claimed plus interest. The Adjudicator
also held that the respondents' letter of 21 December 2000 was not a payment
notice within the meaning of Clause 17(e) of the contract or a withholding
notice within the meaning of Clause 17(g). He also held that he did not have
jurisdiction to decide issues arising out of the respondents' letter of 11
January 2001. The Adjudicator's final decision was given on 17 May 2001.
- On 23 May 2001,
the respondents served notice, pursuant to Clause 17(g) of the contract, of
intention to withhold payment of the sum awarded. They claimed that having
taken over the sub-contract works pursuant to Clause 20(c), they were entitled
to deduct from monies otherwise due to the appellants the reasonable cost
of completing the works. The respondents had paid £303,000 plus VAT to Aderley
Process Technologies Ltd ("APT") to complete the work. That was a larger sum
than the sum awarded by the adjudicator and the appellants were not entitled
to any payment, it was submitted.
- The present
proceedings were instituted by the appellants on 24 May 2001 to enforce the
adjudicator's decision. The issue was whether the defence of set-off was available
to the respondents. The appellants conceded that, if it was available, the
respondents had an arguable counterclaim based on their allegations that the
appellants were in breach of contract in failing to do the work in time and
that, under the contract, the respondents were entitled to engage APT to complete
the work at the sum agreed with them. It was also claimed by the respondents
that the sum of over £30,000 paid to a third party on 30 November 2000 could
be set off against the appellants' claim or form the basis for a counterclaim.
The respondents sought summary judgment in respect of the sums of £303,000
paid or payable to APT and the £30,963 paid to the appellants' steel supplier.
An interim payment was sought having regard to the excess of the respondents'
claim over that of the appellants.
- The appellants
submit that the adjudication, while an ad hoc referral, was under the procedure
set out in Clause 27 of the contract. The decision of the adjudicator was
"final and binding" pursuant to Clause 27 of the contract and should be enforced
by the Court as if the Act applied. Further, a set-off could only be taken
into account if the procedure set out in Clause 17(g) of the sub-contract
had been followed and the respondents had failed to serve a withholding notice
in accordance with the Clause.
- The relevant
provisions of the sub-contract, as set out in the judgment of Judge Kirkham,
and with the addition of the first paragraph of Clause 27a are:
"Clause
1 sets out various definitions, including
'1f.
"Adjudicator" means the person referred to and so called in clause 27
1g.
"Sub-Contract Dispute" means any disagreement or difference between
[Parsons] and [Purac] arising under the Sub-Contract in relation to
any matter in connection with a "construction operation" as defined
in the [Act] including any dispute as to whether the matter referred
to the Adjudicator is in connection with a Construction Operation. ¼
1m. "Final
Date for Payment" means the date determined in accordance with Clause
17(h)(1).
17f. Subject
to Clauses 11(e), 11(f), 20(c) and 31 and as hereinafter provided and
without prejudice to any rights which exist [Purac] shall be entitled
to withhold or defer payment of all or part of any sums otherwise due
under the provisions hereof where:
- any
work done or Plant supplied by [Parsons] is not in accordance with
the Sub-Contract then [Purac] may withhold the cost and expense
of making good the defect in question. If without reasonable cause
[Parsons'] performance of the Sub-Contract falls behind the approved
programme of work then [Purac] may withhold the reasonable value
of the Sub-Contract Works which ought to have been performed in
accordance with the approved programme of work but which at the
relevant stage in the programme of work remained undone.
- A
dispute arises or has arisen between [Parsons] and/or [Purac] and
the Purchaser involving any question of any matter included in any
such application.
17
g. If [Purac] intends to withhold payment of a sum that has become
due under the Sub-Contract in connection with a Construction Operation
or otherwise then not later than one day before the Final Date For Payment
of that sum [Purac] shall serve a notice specifying:
- the amount
proposed to be withheld and the ground for withholding payment or
- if there
is more than one ground, each ground and the amount attributable to it.
Provided
that such notice will not be required if the notice mentioned in Clause
17e complies with the requirements in sub clauses (a) and (b) above.
17
h. (i) [Purac] shall pay [Parsons] any amount due under the
Sub-Contract 14 days after the date upon which the sum became due
(the Final Date for Payment). Provided that where the matter in
respect of which payment is to be made is not a "construction operation"
within the definition provided by the Housing Grants Construction
and Regeneration Act 1996 or the Purchaser becomes insolvent within
the definition of "insolvent" provided by section 113 of the Housing
Grants Construction and Regeneration Act 1996 [Purac] shall have
no obligation to make any payment to [Parsons] except to make payment
within 14 days after the date upon which [Purac] receives payment
in respect of the sum due in respect of the sub-contract works.
¼
20
a. If [Parsons]:
- fails
to proceed with the Sub-Contract Works with due diligence; or
- fails
to execute the Sub-Contract Works or to perform his other obligations
in accordance with the Sub-Contract; or
- refuses
or neglects to remove defective materials or make good defective work
after being directed in writing so to do by [Purac]; or
- commits
an act of bankruptcy or enters into a deed of arrangement with his creditors
or, being a company calls a meeting of its creditors, becomes subject
to an Administration order, has a receiver appointed to manage its affairs
by the holder of a charge or debenture or has a liquidator appointed,
(other than a voluntary liquidation for the purposes of reconstruction),
then in any such event and without prejudice to any other rights or
remedies, [Purac] may by written notice to [Parsons] forthwith to determine
[Parsons'] employment under this Sub-Contract and thereupon [Purac]
may taken possession of all materials, plant and other things whatsoever
brought on to the Site or in respect of which [Parsons] has received
payment under Clause 17 and may use them for the purpose of executing,
completing and maintaining the Sub-Contract Works and may, if he thinks
fit, sell all or any of them and apply the proceeds in or towards the
satisfaction of monies otherwise due to him from [Parsons].
- Upon such
a determination, the rights and liabilities of [Purac] and [Parsons]
shall, subject to the preceding Sub-Clause, be the same as if [Parsons]
had repudiated this Sub-Contract and [Purac] had by his notice of determination
under the preceding Sub-Clause elected to accept such repudiation.
- [Purac]
may in lieu of giving a notice of determination under this clause take
part only of the Sub-Contract Works out of the hands of [Parsons] and
may by himself, his servants or agents, execute, complete and maintain
such part and in such event [Purac] may recover his reasonable costs
of doing so from [Parsons], or deduct such costs from monies otherwise
becoming due to [Parsons].
Clause
27 sets out a procedure for adjudication. It is a bespoke adjudication
scheme, but is compliant with S.108 of the Act.
27
a. Either party shall have the right to refer any sub-contract dispute
for adjudication in accordance with the procedure set out in this Clause
¼ .
27
g. The decision of the Adjudicator shall he complied with forthwith
upon receipt.
[DELETE
ONE OF THE FOLLOWING BEFORE ISSUING TENDER]
h. (i) The
decision of the Adjudicator shall be final and binding; or
(ii) The
decision of the Adjudicator shall be binding on the parties and
they shall comply with it until the dispute is finally determined
by legal proceedings, by arbitration or by agreement between the
parties.
(iii)
If one of the above options 27h(i) or 27h(ii) has not been deleted
then 27h(i) shall apply.
[Neither
(i) nor (ii) had been deleted.]
28
a. Where clause 27h(i) does not apply and subject to the provisions
of clause 27 herein if any dispute arises between [Purac] and [Parsons]
in connection with this Sub-Contract, it shall, subject to the provisions
of this Clause, be referred to arbitration. ¼
- Nothing
contained in this Deed whether expressly or by incorporation or by implication
shall in any way restrict [Purac's] equitable or common law rights of
set off. Without prejudice to the generality of the foregoing, [Purac]
shall have the right to set off against any sum due to [Parsons] whether
hereunder or otherwise a fair and reasonable sum in respect of or on
account of any claim or claims that have been made or which are to be
made against [Purac] by the Purchaser the subject matter of which touches
or concerns the Sub-Contract Works.'"
Appellants' claim
for summary judgment
- The appellants
submit that the referral to adjudication was on the basis that the decision
of the adjudicator should be "final and binding" under Clause 27h(i) and that
the decision "shall be complied with forthwith upon receipt" under Clause
27g. While the adjudication was not under the Act it should be treated as
if given under the Act to the extent that the terms of the sub-contract should
be construed on the basis that the parties intended a swift resolution of
disputes. The respondents had not complied with the contractual procedure
which would have enabled them to set-off (Clause 17g).
- The adjudicator
had found, and it is accepted that his finding is not susceptible to challenge,
that no Clause 17g notice was served by 16 February, that is the date by which,
on the adjudicator's finding, the sum he found due on adjudication was payable.
The respondents submit, however, that they have followed the procedure under
Clause 17g by their notice of 23 May 2001 which was given before they were
obliged to give effect to the adjudicator's final decision of 17 May. They
make the further, and more basic, point that the procedure specified in Clauses
17f and 17g is expressly made subject to Clause 31 which preserves the respondents'
equitable and common law rights of set-off. In Modern Engineering v Gilbert-Ash
[1974] AC 689, 718E, Lord Diplock stated:
"So
when one is concerned with a building contract one starts with the presumption
that each party is to be entitled to all those remedies for its breach as
would arise by operation of law, including the remedy of setting up a breach
of warranty in diminution or extinction of the price of material supplied
or work executed under the contract. To rebut that presumption one must be
able to find in the contract clear unequivocal words in which the parties
have expressed their agreement that this remedy shall not be available in
respect of breaches of that particular contract."
- The appellants
respond that Clause 31 merely restates the position under the contract and
is declaratory of rights expressed in the contract. Moreover, if it was to
be relied on, it was necessary to follow the procedure in Clause 17g. A clause
similar in wording to Clause 17g appears in the form of sub-contract issued
by the Civil Engineering Contractors Association (October 1998) but there
is no equivalent of Clause 31 in that form. In support of the submission that
Clause 31 does not provide an overriding contractual right to set-off, reference
is made to the fact that the expression "subject to Clause 31" does not expressly
govern Clause 17g which provides a procedure, it is submitted, which must
be followed whenever a right to set-off is claimed to negative the obligation
under Clause 27g. Upon the submission to the adjudicator in fact made, Clause
27g operates to require compliance with his decision forthwith.
- I have not found
the question an easy one. When parties provide, in this context, a specific
procedure by which a claim to withhold payment is to be notified (and detailed),
it cannot readily be concluded that the effect of a general clause such as
Clause 31 is to make the procedure unnecessary.
- I have, however,
come to the conclusion that failure to give a notice under Clause 17g is not
fatal to the respondents' right to set-off. Clauses 17f and 17g must be read
together, 17g providing a mechanism whereby the respondents can exercise the
right conferred in 17f. The expression "subject to Clause 31" governs both
paragraphs and maintains the express preservation of rights of set-off in
Clause 31. The expression "nothing contained in this deed shall in any way
restrict" in Clause 31 is consistent with the procedure in Clause 17g being
subject to it. In my view, the judge reached the correct conclusion. It is
open to the respondents to set-off against the adjudicator's decision any
other claim they have against the appellants which had not been determined
by the adjudicator. The adjudicator's decision cannot be re-litigated in other
proceedings but, on the wording of this sub-contract, can be made subject
to set-off and counterclaim. It is accepted that the respondents' counterclaim,
if they are entitled under the terms of the sub-contract to set it off against
the claim, is arguable.
- If that approach
is correct, it is unnecessary to decide whether the purported notice of 23
May 2001 complied with Clause 17g of the sub-contract. The notice must be
served "not later than one day before the final date for payment" in respect
of a sum "that has become due under the sub-contract". The "final date for
payment" is defined in Clause 17h as being "14 days after the date upon which
the sum became due". On behalf of the respondents, it is submitted that the
sum became due upon the adjudicator's final decision on 17 May 2001. The judge
held that "the sum claimed [by the appellants] is a sum determined by the
adjudicator, it is not a sum due under the sub-contract. Accordingly, it falls
outwith the definition of 'final date for payment'."
- I do not propose
to decide the point and would need to consider further the provisions in the
sub-contract as to money becoming due before doing so. I do however express
my doubts about both the propositions set out in the previous paragraph. The
fact that it is an adjudicator who decides that the payment should be made
does not on the face of it make it any less due under the sub-contract which
has provided for his appointment. It may also have become due under the sub-contract
on a particular date even if that date is only determined by the adjudicator
at a later date. I leave the point open.
- The extent of
the right to set-off under Clause 17f does not, on my findings arise.
Application to
stay respondents' claim to arbitration
- The appellants
submit that Clause 28 of the sub-contract is a binding arbitration clause.
The dispute raised upon the respondents' claim was entirely separate from
that determined by ad hoc adjudication. The respondents' claim was not submitted
to adjudication. Moreover, Clause 27 could have no application because (notwithstanding
the appellants' reliance on Clause 27 on other issues), the work was not a
"construction operation" within the meaning of Clause 1g and Clause 27. That
being so, it is submitted, Clause 28 should be read as if Clause 27 was not
present in the contract and provides a binding arbitration clause.
- I cannot accept
that submission. The fact that it was later decided by an adjudicator that
the sub-contract work was not a construction operation does not permit a party
to treat the sub-contract as if Clause 27 was absent so that the reference
to it in Clause 28a can be ignored. The opening words of Clause 28a refer
to Clause 27 and require arbitration only "where Clause 27h(i) does not apply".
When the parties entered into the contract they did not delete Clause 27h(i)
with the result that by virtue of Clause 27h(iii) that paragraph "shall apply".
Clause 28a can, by the terms, operate only where Clause 27h(i) does not apply.
Judgment on Part
20 claim and interim payment
- It is conceded
that upon proof of a relevant breach of contract under Clause 20 the respondents
were entitled to take the remainder of the sub-contract works out of the hands
of the appellants under Clause 20c. The sub-clause was probably intended primarily
to apply to a situation where a part of the works was to be left with the
sub-contractor but it is agreed that the clause is capable of covering the
circumstances of this case. The issues arising were essentially issues of
fact for the judge. It is submitted that by using the expression "on balance"
in relation to the respondents' entitlement to invoke Clause 20c, the judge
has applied the wrong test to an application for summary judgment (Swain
v Hillman [2001] 1 All ER 91). The judge erred in conducting a "mini trial",
it is submitted. It is further submitted that there was evidence that the
appellants' performance of the sub-contract was delayed or prevented by the
conduct of other sub-contractors and also that no loss arose from any delay
by the appellants because other sub-contractors were not ready to accommodate
the appellants' work.
- I do not consider
that the judge's use of the expression "on balance" affects the validity of
her conclusion. She plainly had in mind the correct test and referred to Swain
v Hillman. In her judgment of 21 August 2001, the judge carefully considered
the considerable evidence before her. The appellants' own material revealed
substantial breaches of the obligations in Clause 20. The judge rightly held
that the issue was whether the breaches entitled the respondents to take over
the work pursuant to the clause and questions as to whether the appellants'
delays were causative of other delays were not relevant. The judge was entitled
to conclude that the appellants had "no real prospect of successfully defending
[the respondents'] claim" for the cost of completing the work. She noted that
the respondents' entitlement to credit for payment to the steel supplier was
not disputed. There was no error law by the judge and she was entitled, on
the evidence, to reach the conclusion that the respondents were entitled,
to the extent of those two claims, to summary judgment.
- Moreover, on
the material before her, the judge was entitled, in her discretion, to make
an interim award of £12,000 in the respondents' favour. The judge acknowledged
that credit should be given to the appellants for the amount awarded to them
by the adjudicator. The figures were such that a modest interim award could
properly be made. Amongst other things, the appellants' calculation of the
value of outstanding work was close to the sum of £303,000 held to be payable
to APT. There was a substantial difference, in the respondents' favour, between
the amount claimed by them and the amount claimed by the appellants.
- I would dismiss
the appeal.
Lord
Justice Mummery:
- I agree.
Lord
Justice Latham:
- I also agree.